Camden Snowbowl loses $210k

Camden Snowbowl loses $210k

Postby gondicar » Tue Apr 26, 2016 9:46 pm

The Snow Bowl incurred a $210,000 deficit this past winter because of warm weather and a scarcity of snow. The Snow Bowl had a deficit of $80,000 in the previous year.

http://bangordailynews.com/2016/04/26/n ... l-deficit/
Access to recreational sports is integral to a well-rounded life. Maine Adaptive Sports & Recreation is a year-round program teaching adaptive skiing and other sports activities to people with disabilities ages 4 and up: http://www.maineadaptive.org/
User avatar
gondicar
Sugarloafer
 
Posts: 2355
Joined: Tue Aug 26, 2008 9:11 am

Re: Camden Snowbowl loses $210k

Postby b632 » Sat Apr 30, 2016 6:46 am

Ouch! I have to make it a point to go ski it next winter.
Stop thinking and end your problems. -Lao Tzu
b632
Sugarloafer
 
Posts: 2474
Joined: Mon Nov 13, 2006 2:37 pm
Location: Portland Me

Re: Troubles in Camden

Postby Glade Monkey » Wed Apr 26, 2017 5:42 pm

http://www.newenglandskiindustry.com/viewstory.php?storyid=565

Though ski season ended a month ago, the coastal town of Camden, Maine is swirling in controversy following financial and environmental scandals involving Camden Snow Bowl.

Camden's town manager and the Snow Bowl's general manager both resigned this winter due to issues involving the ski area. As a result of the Snow Bowl's financial problems, the town was forced to borrow $2.5 million to cover its cash fund shortfall.

The $6.5 million Ragged Mountain Redevelopment Project was kicked off in November of 2013, when town voters approved a $2 million bond to be matched with $4.5 million in private contributions from the Ragged Mountain Foundation. The project was to include new trails, the installation of two used chairlifts, expanded snowmaking, expanded night skiing, and a new base lodge. Construction at the town owned and operated ski area commenced in March of 2014 under the watch of new General Manager Landon Fake.

The aggressive first phase of the project, which involved removing the area's entire lift network and installing two chairlifts, quickly fell behind schedule. The area was able to only able to complete one chairlift that winter, as its new summit triple opened on January 29. The postponed start of the season resulted in the refunding of 145 season passes.

While the $2.6 million lodge project was scheduled for the 2015 off season, the only major project undertaken was to complete the partially installed novice chairlift.

No significant work was completed during the 2016 off season. As of December 16, town manager Patricia Finnigan reported that $6,811,363 had been spent on the project and that the latest lodge construction estimate was an additional $2.7 million. Finnigan resigned the following month. One week later, Fake resigned.

In February, the Department of Environmental Protection fined the town of Camden $44,400 for forest destruction and erosion issues tied to the ski area expansion.

According to an audit conducted by RHR Smith & Company, the Town of Camden "paid approximately $750,000 in project expenses beyond the amount approved by the voters," not including the $2.6 million budgeted lodge project. The audit also uncovered questionable accounting practices.

The recent Camden Snow Bowl issues have a stark similarity to those at other government operated ski areas.

State of New Hampshire owned and operated Cannon Mountain's Mittersill expansion project resulted in the clearing of Federally preserved forest and erosion caused by heavy equipment. In addition, an audit released just over a year ago disclosed missing funds and accounting issues. Both Camden and Cannon have also consumed public general funds for capital projects and operating deficits in recent years.

Meanwhile, Belknap County owned and operated Gunstock Mountain is facing scrutiny from the county delegation over its debts and deficits. One current proposal is a half decade moratorium on expansion debt for the ski area, as well as the development of an operating cash reserve fund to curb annual requests for off season operating cash. Gunstock needed a $950,000 bridge loan in 2016 after posting a $954,145 loss on operations.

While Camden Snow Bowl's proposed $874,000 operating budget was recently recommended by the Camden Budget Committee, town Select Board is facing mounting criticism for its lack of oversight.

One Budget Committee member told the Select Board, "One consideration ought to be that none of you run again for this office."

In response, two members of the four person Select Board said they will not seek re-election.
Ski season is too short
User avatar
Glade Monkey
Sugarloafer
 
Posts: 1047
Joined: Mon Nov 29, 2010 4:36 pm
Location: Southern Maine


Return to The Camden Snowbowl discussion

Who is online

Users browsing this forum: No registered users and 1 guest